Investor: NAVAL-BOX-CAL d.o.o.
Contractor: Strabag d.o.o.
Production complex for assembly of modular containers with supporting facilities – Phase 1 includes:
Facility "B1" – assembly and equipping workshop for modular containers, consisting of production area, open covered canopy – temporary storage, two administrative-social-technical zones, and three mezzanines for storage of machinery equipment, total gross developed building area (GBA) Pbr=42,635.00 m²;
Facility "B3" – security post, total gross developed building area (GBA) Pbr=50.00 m²;
Facility "B4" – sprinkler and hydrant pump station with reservoirs, total gross developed building area (GBA) Pbr=375.00 m²;
Facility "B5" – canopy for storing technical gas cylinders, total gross developed building area (GBA) Pbr=50.00 m²;
Facility "B6" – MEP (Mechanical, Electrical, Plumbing) facility, total gross developed building area (GBA) Pbr=75.00 m²;
Heliport, 491 m² area